Coal India to fund construction of rail network to link coalfields

In a first, Coal India Ltd (CIL), the world’s largest coal miner, is set to fund construction of a large rail network connecting the country’s coalfields. For this, CIL would float a special-purpose vehicle ( SPV) that would lay a 180-km line for evacuating coal currently blocked in Chhattisgarh. To cover its investment, in yet another first for the miner, it is planning to levy a user charge, marking its entry into haulage business.

While CIL would hold 64 per cent stake in the SPV, the rest would be shared between Ircon, a company under the rail ministry, and the Chhattisgarh government. The move is part of a bigger plan being implemented under the PMO’s watch to set up three rail lines, running 300-km across three naxal-affected but coal-rich states of Chhattisgarh, Odisha and Jharkhand. The PMO has asked the coal, environment and rail ministries to complete the project in three years to free up 300 mt coal supply.

“This is an unprecedented move by CIL to ramp up supply. We will fund an arterial rail line running 180 km across coalfields. So far, we have built only small railway sidings of less than 10 km for in-house use,” CIL Chairman S Narsing Rao told Business Standard. He said the miner would fund 64 per cent, or Rs 2,880 crore, of the Rs 4,500-crore cost for building the double-line broad-gauge Bhupdeopur-Korba-Dharamjai rail corridor. The decision was taken at a recent meeting of the PM’s principal secretary, Pulok Chatterjee, with Rao, secretaries of the coal and environment ministries and Railway Board Chairman Vinay Mittal.

EXPLORING POSSIBILITIES
•Untapped reserves: CIL to float SPV to build 180-km rail network for evacuating 37 bt coal lying untapped in Chhattisgarh’s Mand-Raigarh coalfield; to fund 64% of the Rs 4,500-cr cost
•Haulage: To levy user charges on consumers to cover cost, marking entry in the haulage business. MoU to be signed between CIL and rail ministry
•Larger plan: Move part of the plan to increase availability by additional 300 mt by laying a 300-km rail network in three states under PMO’s watch
•Next on cards: Another 93-km line to be laid with an investment of Rs 1,095 cr to connect North-Karanpura coalfield in Jharkhand to free up another 127 mt coal. Stage-I forest clearance obtained from the environment ministry in April 2011
•More ahead: The third, a 53-km line will connect Odisha’s Ib Valley coalfield, only 15% of whose 132-mtpa capacity is currently utilised. PMO has asked rail ministry to seek CM Naveen Patnaik’s intervention for clearances

Rao said the CIL subsidiaries had approved the funding proposal. The details of the user fee to be charged on companies in the power and steel sectors, a completely new concept, were being worked out. It had been decided CIL would finalise a Memorandum of Understanding with the rail ministry on the projects funded by the miner. The MoU would cover the financial obligation on CIL and the operational responsibility of the railways.

The line would connect the eastern and western corridors of Chhattisgarh’s Mand-Raigarh coalfield, which houses 37 billion tonnes of high-grade reserves. The field has a production potential of 40 mt a year. The Planning Commission has granted in-principle approval for a 63-km section of the line.

As part of the plan, two more lines, covering 146-km would be laid to connect Jharkhand’s North Karanpura coalfield with Odisha’s Ib Valley. Chatterjee has started quarterly review of the progress of the overall project.

http://www.business-standard.com/india/news/coal-india-to-fund-constructionrail-network-to-link-coalfields/498393/

Advertisements
Published in: on January 12, 2013 at 5:18 pm  Comments (1)  
Tags: ,

The URI to TrackBack this entry is: https://indianrlys.wordpress.com/2013/01/12/coal-india-to-fund-construction-of-rail-network-to-link-coalfields/trackback/

RSS feed for comments on this post.

One CommentLeave a comment

  1. great news , both are great companies in India…


Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s

%d bloggers like this: